<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=192888919167017&amp;ev=PageView&amp;noscript=1">
Wednesday,  November 27 , 2024

Linkedin Pinterest
Check Out Our Newsletters envelope icon
Get the latest news that you care about most in your inbox every week by signing up for our newsletters.
News / Clark County News

City works to try to prevent repeat of sewage spills

Vancouver officials find out birds, humans triggered fall incidents

By Katy Sword, Columbian politics reporter
Published: May 16, 2018, 6:08am
2 Photos
Problems at Vancouver’s Westside Wastewater Treatment facility resulted in the spillage of 600,000 gallons of untreated sewage into the Columbia River in the fall of 2017. Two spills occurred within four weeks.
Problems at Vancouver’s Westside Wastewater Treatment facility resulted in the spillage of 600,000 gallons of untreated sewage into the Columbia River in the fall of 2017. Two spills occurred within four weeks. (Photo contributed by city of Vancouver) Photo Gallery

Birds and humans were separately responsible for the release of nearly 500,000 gallons of untreated sewage into the Columbia River last fall. Now the city is looking at ways to ensure neither incident ever happens again.

On Sept. 30, nearly an Olympic-sized pool worth of raw sewage left Vancouver’s Westside wastewater treatment facility in what city staff consider a rare occurrence. A similar event had not taken place for at least 26 years. But then it happened again on Oct. 25 when 80,000 gallons of sewage were released, although the two instances were unrelated.

At the time, the specific causes were hazy. Months later, the city of Vancouver has some answers. And ideally, staff will make improvements to prevent sewage from ever again flowing freely into the river.

What happened

Sometime before Sept. 30, several cross arms used to keep power lines separate were replaced with narrower pieces by Clark Public Utilities near the treatment plant. When dozens of birds congregated that warm Saturday, something scared them, said Dan Swensen, the city’s engineering and construction services manager.

The flock took off in all directions, which caused the lines to swing. The swinging lines hit each other three times, which caused the circuit breaker to turn off and try to re-engage — three times. Both the circuit breaker and backup generators operate on a 10-second timer, Swensen said they later discovered.

“After the third time, the computer was so confused, it just quit,” he said.

That interruption in systems power resulted in the sewage release.

Less than a month later, some routine maintenance was scheduled at the same treatment plant.

Sensors in a wet well needed to be recalibrated. A company, Jacobs, was hired to do the work. Jacobs staff called the control room to turn off the sensors while the maintenance was completed, but somehow the sensors were not taken offline, Swensen said.

The sensors began reading that water was coming into the well and started pumping water out, even though the levels were actually decreasing. This continued until the well ran dry and introduced air into the system. Swensen said this caused the system to stop, and before they could manually repair the system, untreated water was released.

Changes made

City staff and Jacobs, the subcontractor with CH2M, are taking this opportunity to re-evaluate their process and make any necessary infrastructure improvements.

For example, staff reset the generator timer to restart after five seconds to offset with the circuit breaker timers to avoid any future timing issues. Any work on the wet well and pumps by contractors from Jacobs will be supervised by a staff operator to ensure water levels remain sufficient. Communication and notification procedures will also be updated.

To prevent a future bird incident, Swensen said, operators are talking with Clark Public Utilities to put spacers between the power lines so if they move, they move together, thus preventing any power surges.

The city is also in the process of designing an independent emergency pumping system that would ensure that wastewater goes through the treatment process regardless of the primary pumping system’s status.

Staff is also working toward a $12.5 million project to modernize the system control and data acquisition system, as well as a $10 million electrical system overhaul.

Some city councilors want to see more done.

“The one thing I didn’t hear is what the city is going to do better,” said Councilor Alishia Topper. “It took us more than four days to inform residents in the community about the occurrence.”

Topper also asked for staff to consider how much it would cost to completely overhaul the wastewater treatment plant and ensure it’s in working order.

“I know those price tags can be big … but I still would be interested in seeing those numbers,” she said.

Councilor Bart Hansen asked that the city evaluate all of its facilities to see what backups exist and take a more holistic approach.

“Whether it be birds, whether it be cars, tornadoes, hurricane winds, snow, whatever you might like it to be, the idea that you completely rely on someone else to control your destiny is a little bit difficult,” Hansen said. “You’ve got to have an adequate backup in order to address those issues.”

Loading...
Tags
 
Columbian politics reporter