<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=192888919167017&amp;ev=PageView&amp;noscript=1">
Wednesday,  June 26 , 2024

Linkedin Pinterest
News / Nation & World

Pedestrian bridge was over budget, late after design change

Placement for main support had been reworked

By JASON DEAREN and JENNIFER KAY, Associated Press
Published: March 20, 2018, 10:02pm
4 Photos
FILE- This March 10, 2018 file photo shows the main span of the a pedestrian bridge being positioned to connect the City of Sweetwater to Florida International University near Miami. The 950- ton new bridge collapsed, Thursday, March 15, 2018, over several cars causing fatalities and injuries. Documents obtained by The Associated Press through a public records request show that the Florida Department of Transportation in October 2016 ordered Florida International University and its contractors to move the bridge’s main, signature pylon 11 feet north to the edge of a canal, widening the distance the crossing would gap between its supports and requiring a new base structural design.
FILE- This March 10, 2018 file photo shows the main span of the a pedestrian bridge being positioned to connect the City of Sweetwater to Florida International University near Miami. The 950- ton new bridge collapsed, Thursday, March 15, 2018, over several cars causing fatalities and injuries. Documents obtained by The Associated Press through a public records request show that the Florida Department of Transportation in October 2016 ordered Florida International University and its contractors to move the bridge’s main, signature pylon 11 feet north to the edge of a canal, widening the distance the crossing would gap between its supports and requiring a new base structural design. (Pedro Portal/ The Miami Herald via AP) Photo Gallery

MIAMI — Construction of the pedestrian bridge that collapsed and killed six people in the Miami area was behind schedule and millions over budget, in part because of a key change in the design and placement of one of its support towers.

Documents obtained by The Associated Press through a public-records request show that the Florida Department of Transportation in October 2016 advised Florida International University and its contractors to move one of the bridge’s main support structures 11 feet north to the edge of a canal, widening the gap between the crossing’s end supports and requiring new structural design.

The span’s signature, 109-foot-tall pylon was to be built atop a base at the span’s northern end. It was designed for basic support and to contribute to the aesthetics of the bridge, which was touted as an architectural marvel that would connect the rapidly growing university to the nearby community of Sweetwater. In their winning 2015 proposal, designers said the bridge provided “spectacular views” for both pedestrians using the bridge and drivers passing beneath it. They added that the tower could serve as a safety feature because it would have an “eagle-eyed location” for additional lighting and security cameras.

Videos of Thursday’s collapse show that the concrete, prefabricated segment of the bridge started crumbling on the same end of the span where the tower redesign occurred, two days after an engineer on the project reported cracks in the same location. The segment that failed had been placed atop the pylon’s footing, and the taller tower section was to be installed later.

U.S. Transportation Secretary Elaine Chao has ordered her department’s inspector general to audit the bridge, according to a news release Tuesday from the U.S. Department of Transportation. The agency awarded millions of dollars to the project.

It is unclear if the design change contributed to the failure. But emails between the school, contractors, Sweetwater city officials and permitting agencies show a project that was behind schedule, which had officials worried that further delays could jeopardize the federal funding.

When the bridge collapsed, the project was already running about $2.6 million over its $9.4 million initial budget, cost-tracking documents from February show. Originally to be completed in July, the finish date had been pushed to January 2019.

Difficulties began in late 2016, when the Florida Department of Transportation emailed project officials saying they wanted room to allow for future widening of the U.S. highway under the bridge, according to the documents. The new position of the tower would be on the north side.

“This … places the current location of the pylon in conflict with the extra travel lane and would require bridge design modifications,” Alfred Reyna, a transportation department employee working on the bridge project, wrote in an email.

Loading...