A look at how much money had been spent on the Columbia River Crossing at key milestones in the project:
o Draft Environmental Impact Statement (May 2008): $45,910,247.
o Selection of Locally Preferred Alternative (July 2008): $52,673,931.
o Final Environmental Impact Statement (September 2011): $133,820,175.
o Federal Record of Decision (December 2011): $139,373,078.
o Washington pulls out of project (June 2013): $188,212,254
o Total cost to date (through March 31): $196,614,118.89.
SOURCE: Oregon Department of Transportation
By the time the Columbia River Crossing locks its doors for good next month, taxpayers may end up spending more than $200 million on an effort that never turned a shovel toward actual construction.
The proposed Interstate 5 Bridge replacement project had racked up $196.6 million in planning costs through March 31, according to the Oregon Department of Transportation. Additional accrued and estimated costs into April pushed that number to $199.5 million.
As the CRC shuts down, project officials have offered the clearest picture yet of where all that money went over the course of a decade. A comprehensive list of 171 consultants, individuals and public agencies that were paid to work on the CRC was released this week in response to a records request by The Columbian.